The councillor for sports, Victor Ferrández, has announced that the firm
contracted to demolish the main stand at Torrevieja’s football stadium has
begun its business. The work started with the demolition of the roof and a
crane has been sent in to dismantle it. The main indoor grandstand and
changing rooms are all due to be demolished and there will be disconnection
of all utilities.
Asbestos also needs to be removed from the site which will be left good
following the removal work. The demolition is expected to be complete by the
end of August. There are plans to replace some of the facilities and to ensure
that the team has somewhere they can play in future.
Councillor Ferrández has explained that in the new football season it is hoped
that the field will be back to normal and that the second phase can begin of
drafting a new project which will allow for new seating to be developed and
the stadium to have more modern facilities.
The need to demolish the stand and team locker room is nothing new. In 2014
it was recognised that there were deficiencies in the building work and a
technical report suggested that measures should be taken to limit the use of
the stand and accompanying locker room.
The stand did not, in fact, have a licence and it would have been too
complicated to have made the corrections necessary to enable one to be
applied. Instead it was decided that demolition and rebuilding would be a
better option. A minor contract has now been issued for a drafting of the
project and work is being carried out following the approval of the 2018
budget.